Construction Projects - 2019

Print
Press Enter to show all options, press Tab go to next option

Construction Guy 

ROE AVENUE WILL CLOSED April 15 to April 25

TO CONSTRUCT BRIDGE APPROACHES AND

PLACE AN EPOXY COATING ON THE BRIDGE DECK.

PRAIRIE VILLAGE CONSTRUCTION REPORT

Updated: April 15, 2019

Capture Weather by weatherundergound

A postcard will be sent to each resident prior to major construction beginning on their street.


CARS Program (for Arterial Streets)

General Information
The County Board of Commissioners recognized that one of the keys to the success of Johnson County is in its major transportation corridors that connect the cities of Johnson County. In response to this need the Board created the County Assistance Road System (CARS) program.  This program provides funds to the cities of Johnson County to construct and maintain major arterial roadways. The County pays 50% of the project’s construction and construction inspection costs. Cities are responsible for design, right-of-way, and utility relocation costs.

 2019 CARS Program Contractor: TBD 
 Roe Avenue, 63rd Street to 67th Street Start Date: April 2019 
 Construction Cost:$1,000,000 Completion Date: Fall 2019
 The project will consist of full curb replacement and street reconstruction.

 

Apr 15: WaterOne will begin work on 4 waterline crossings on April 22nd.  This will upgrade their facilities prior to the City roadway improvements.  Daily road closures will be necessary during this 4-5 week construction period.

Apr 1: The project will be ready for contractors to bid on this month. 

Jan 29: The project is currently in design. Staff is coordinating utility relocations at this time.

 

2018 CARS Program  Contractor: O'Donnell and Sons
   Start Date: June 2018
 Construction Cost: $2,400,000  Completion Date: Spring 2019
  The 2018 CARS PROGRAM consists of 2 projects. 

Email the project team at pvstreets@odonnell-sons.com.

 This email goes to the Contractor and City staff and
we work together to get your concern addressed in a timely fashion. 
 Mission Road, 85th Street to 95th Street (with the City of Leawood)
 The project will consists of minor curb repair and driveway replacement on the west side. The east side will replace curb south of 92nd Street and install new sidewalk.  This project will not mill/overlay the roadway until Johnson County Wastewater has completed a planned infrastructure replacement scheduled for late 2021.  The mill and overlay will occur sometime in 2022. 

 

Apr 19: Project is Complete. Thank you for your patience during construction. Remaining traffic control on site is for other projects. 

Apr 15: Micro surface has been laid and pavement markings are now complete. We anticipate removal of the traffic cones this week.

Apr 1: Crews will be back April 3-4 to micro surface Mission Road. This process will take 2 days.  Pavement markings will be applied after the surface has properly cured.

Jan 29:  Crews will be back in the spring for the remaining paving item. The roadway will be micro surfaced and fresh pavement markings will be applied.

 Roe Avenue, 67th Street to 75th Street
 The project will consist of curb repair, sidewalk replacement and driveway apron replacement as needed.  Bridge repairs are included in the project along with 8 parking spots added along Roe in the vicinity of the shelter at Porter Park. A public meeting was held on July 12th from 4:30 pm to 6:30 pm at the Community Center. 

 

Apr 15: Residents on the east side with substantial shade received a notification regarding sod vs shade mix seed.  Please contact the project team at pvstreets@odonnell-sons.com.  Sod is going down on the east side and the west side concrete is substantially complete with some sidewalk left to install.  Concrete is scheduled for completion week of April 22nd.

ROE AVENUE WILL BE CLOSED JUST NORTH OF 75TH STREET APRIL 15 TO APRIL 25 TO CONSTRUCT THE BRIDGE APPROACHES AND PLACE AN EPOXY COATING ON THE BRIDGE DECK.

Apr 1: Crews are back and working on the west side concrete this week.  The east side concrete is substantially complete and all sidewalks are open.  Sod will be placed next week on the east side.  

Mar 15: Crews will be back on site the week of March 25th! 

Jan 29: Crews will be back in the spring for the remaining concrete items and to mill/overlay the roadway.

 


Residential Street Program

 ONCE CONSTRUCTION ACTIVITIES BEGIN ON YOUR STREET,PLEASE REMEMBER TO LOOK FOR ORANGE FLYERS IN YOUR YARD TO NOTIFY YOU OF CONSTRUCTION ACTIVITIES THAT MAY IMPACT YOUR ACCESS.

Email the project team at pvstreets@odonnell-sons.com.

 This email goes to the project team at the Contractor and the City staff.
 We work together to get your concern addressed in a timely fashion.

 

General Information
This is a City program to repair existing streets.  Every street is evaluated based on existing condition and given a numerical rating derived from formulas that take into account the amount and type of distresses in the asphalt pavement. This program will replace existing damaged or deteriorated concrete curb, sidewalks (where there are currently sidewalks), some driveways, new sidewalk where there is none and updating ADA (American’s with Disabilities Act) pedestrian ramps. The existing asphalt pavement will either be: 

  1. Reconstructed full depth, or 
  2.  Mill pavement between two and three inches then resurfaced with two or three inches of asphalt. Full depth pavement repairs will be performed as necessary

During the hot summer months temporary restoration in the right of way will be seed.  The contractor will be back in the fall for permanent restoration of sod.  Below is the list of streets, and their proposed improvements.  Please note that this list (and the proposed treatments) is only tentative and that streets may be deleted or added based on budgetary restrictions. 

Click here to view a full size map of the 2019 Residential Paving Program and hover over your street for updates on the construction activities!

2019 construction

Cedar Street (83rd Terrace to 85th Street)  curb repairs with mill/overlay

"On street" public meeting date March 25 at 5:30 pm for residents.

Mill/overlay April 24th

 Cedar Drive cul-de-sac (off of Somerset) curb repairs with mill/overlay

 "On street" public meeting date March 21st at 5:30 pm for residents.

Removals for curb repairs to start Monday April 22nd.

 Granada (81st to 83rd) curb repair with mill/overlay 
 "On street" public meeting date April 23 at 5:30 pm for residents mid block.
 Windsor Drive (79th to Somerset)  new sidewalk and curbs with mill/overlay
 "On street" public meeting date April 24 at 5:30 pm for residents mid block.

 The following streets have been added to the mill/overlay list and crews will be placing asphalt within the next few weeks.  Please do not park on the street when you receive the orange flyer.

91st Street (Mission to Delmar) April 22nd

90th Street (Roe to Somerset) April 24th

77th Terrace (Lamar to City Limits) April 26th

Dearborn (81st to 83rd) April 25th

 

Norwood Drive (79th Street to Somerset Drive)

 


Concrete Repair Program

Concerns/questions?  Email the project inspector at dthompson@pvkansas.com

General Information
Replacement of existing damaged or deteriorated concrete curb, sidewalk and ADA (American’s with Disabilities Act) pedestrian sidewalk ramps.

 2019 Program  Contractor: TBD
   Start Date: BIDS OPEN MAY 17
 Construction Cost: $700,000  Completion Date: Fall 2019
 2018 Program  Contractor: Kansas Heavy Construction
  Start Date: June 2018 
 Construction Cost: $700,000 Completion Date: Spring 2019 

Apr 15: The contractor has some minor clean up to perform and will be back through the areas completing restoration (seeding) of last years work this week.  Please contact the City if you do not see growth in a few weeks.  Thanks!

Click here to download a larger map of the 2019 Concrete Repair Program.

2019 concrete map for website


 

2019 Street Repair Program

General Information
The City has created a program whereby a Contractor is hired to perform street repairs at various locations throughout the City. This program allows us to address areas where significant settlement or deterioration has occurred and make repairs to the roadway in those areas.  Click here to download a full size Pavement Repair map.

 2019 Program
 Contractor: TBD
   Start Date: BIDS OPEN MAY 1
 Construction Cost: $150,000  Completion Date: Summer 2019

2019 Pavement Repair Map


 

MicroSurfacing/Crack Seal Program

Concerns/questions?  Email the project team at microcrack@pvkansas.com  This email goes to 4 members of the team at the City and Contractor.

General Information
Micro Surfacing is a mixture of emulsified (liquid-like) asphalt, aggregate, admixtures, cement and water that is applied in a thin coat as a maintenance tool to assist in preserving the existing asphalt pavement. It helps seal the existing surface and has a life span of approximately seven to ten years.  It is not considered a substitute for reconstructing or resurfacing the street, but rather a less costly solution in prolonging the existing pavement until major work is necessary and as funding becomes available.

The Contractor will be working on several streets throughout Prairie Village on the same day so we cannot tell you exactly what time the crew will begin on your street.  The first street they work on will be at 8:00 a.m.  After completing that street, they will move to others and will stop Micro Surfacing very early in the afternoon to allow the streets time to dry before the end of the workday.  Please keep in mind that weather is a factor in the schedule and drying time.  The material is very sensitive to water so the weather is monitored closely for pop-up storms. 

There are two very important issues at hand with micro surface:

  1. It is sensitive to water. Please turn off your sprinkler systems the day of the scheduled Micro Surfacing.
  2. Driving on the surface is not permitted until the micro surface is cured; for this reason the street must be closed for the day. Any one driving around the barricades or driving on the street prior to it being opened may be subject to damages.

Be on the lookout for changeable message boards and orange flyers to let you know when the micro surface is scheduled for your street. 

 

Crack Seal is a hot applied flexible rubberized sealant used to seal cracks in the pavement to prevent water from entering the base and sub-grade.  Sealing cracks and joints extends the service life of the pavement.  Streets will not have to be closed for crack sealing; therefore no notification will be given.  Crack Seal is completed in the fall when the cracks have had time to expand to allow the material to enter the cracks entirely.  We anticipate the Crack Seal Program to begin in late October.

Please note that streets on the map may change based on available funding. 

2019 Micro-Crack Program  Contractor: Vance Brothers
   Start Date: May 2019
 Construction Cost: $312,000  Completion Date: November 2019
 View a full page map of the Micro Surface  streets or the Crack Seal streets.

 

 2019 Crack Map2019 Micro Map