Construction Projects - 2019

Print
Press Enter to show all options, press Tab go to next option

Construction Guy 

Roe Avenue

63rd to 67th will be reconstructed this summer.

The roadway will be closed during this complete reconstruction.

Closure is scheduled for June 20, 2019

PRAIRIE VILLAGE CONSTRUCTION REPORT

Updated: June 14, 2019

 A postcard will be sent to each resident prior to major construction beginning on their street.


CARS Program (for Arterial Streets)

General Information
The County Board of Commissioners recognized that one of the keys to the success of Johnson County is in its major transportation corridors that connect the cities of Johnson County. In response to this need the Board created the County Assistance Road System (CARS) program.  This program provides funds to the cities of Johnson County to construct and maintain major arterial roadways. The County pays 50% of the project’s construction and construction inspection costs. Cities are responsible for design, right-of-way, and utility relocation costs.

 2019 CARS Program Contractor:JM Fahey
 Roe Avenue, 63rd Street to 67th Street Start Date: June 20, 2019 
 Construction Cost:$1,000,000 Completion Date: Fall 2019

 The project will consist of full curb replacement and street reconstruction.

Email the project team at ROE6367@pvkansas.com if you have questions or concerns.

 

June 24: Crews are on site today sawcutting the curb. Demo begins this week on sidewalk and west side curb. East side demo of the sidewalk will not impact after hours driveway access.

June 21: The road closure is set up and construction will begin on Monday. No work today due to weather.

June  13:     Public Meeting for adjacent residents

  Community Center | 4:30 pm to 6:30 pm | June 18th

Apr 15: WaterOne will begin work on 4 waterline crossings on April 22nd.  This will upgrade their facilities prior to the City roadway improvements.  Daily road closures will be necessary during this 4-5 week construction period.

Apr 1: The project will be ready for contractors to bid on this month. 

Jan 29: The project is currently in design. Staff is coordinating utility relocations at this time.

 

2018 CARS Program  Contractor: O'Donnell and Sons
   Start Date: June 2018
 Construction Cost: $2,400,000  Completion Date: Spring 2019
  The 2018 CARS PROGRAM consists of 2 projects. 

Email the project team at pvstreets@odonnell-sons.com.

 This email goes to the Contractor and City staff and
we work together to get your concern addressed in a timely fashion. 

 

 Roe Avenue, 67th Street to 75th Street
 The project will consist of curb repair, sidewalk replacement and driveway apron replacement as needed.  Bridge repairs are included in the project along with 8 parking spots added along Roe in the vicinity of the shelter at Porter Park. A public meeting was held on July 12th from 4:30 pm to 6:30 pm at the Community Center. 

 

Jun  21: Sod operations continue and are anticipated to wrap up early next week.

Jun 4:  Underdrain installation on Roe at 71st to address drainage issue.  Paving operations will be completed after this installation. Sodding will continue this week, Thursday.  There is approximately 7 days of sodding left on the project, weather permitting.

May 24: Paving is complete.  Pavement marking operations will continue until complete.  Paving at 71st will be complete after drainage issues are addressed. Sod placement is delayed due to recent rains and will commence as soon as weather permits.

May 10: Deep mill areas are closed to thru traffic with access for residents and emergency vehicles.  Paving operations will continue, weather permitting.

May 3:  Sod crews have been hampered by the recent rains.  Sod placement will start up again as soon as they can get material.  Paving operations start today with the milling crews.  Next week crews will be deep milling.  This will require closures to through traffic.

Apr 26:  Roe Avenue concrete work is complete and now the contractor is focused on sod and paving activities.  The week of May 6th we anticipate milling and paving operations.  Because this is a deep mill the roadway will be closed to through traffic. 

Apr 15: Residents on the east side with substantial shade received a notification regarding sod vs shade mix seed.  Please contact the project team at pvstreets@odonnell-sons.com.  Sod is going down on the east side and the west side concrete is substantially complete with some sidewalk left to install.  Concrete is scheduled for completion week of April 22nd.

ROE AVENUE WILL BE CLOSED JUST NORTH OF 75TH STREET APRIL 15 TO APRIL 25 TO CONSTRUCT THE BRIDGE APPROACHES AND PLACE AN EPOXY COATING ON THE BRIDGE DECK.

Apr 1: Crews are back and working on the west side concrete this week.  The east side concrete is substantially complete and all sidewalks are open.  Sod will be placed next week on the east side.  

Mar 15: Crews will be back on site the week of March 25th! 

Jan 29: Crews will be back in the spring for the remaining concrete items and to mill/overlay the roadway.

 


Residential Street Program

 ONCE CONSTRUCTION ACTIVITIES BEGIN ON YOUR STREET,PLEASE REMEMBER TO LOOK FOR ORANGE FLYERS IN YOUR YARD TO NOTIFY YOU OF CONSTRUCTION ACTIVITIES THAT MAY IMPACT YOUR ACCESS.

Email the project team at pvstreets@odonnell-sons.com.

 This email goes to the project team at the Contractor and the City staff.
 We work together to get your concern addressed in a timely fashion.

 

General Information
This is a City program to repair existing streets.  Every street is evaluated based on existing condition and given a numerical rating derived from formulas that take into account the amount and type of distresses in the asphalt pavement. This program will replace existing damaged or deteriorated concrete curb, sidewalks (where there are currently sidewalks), some driveways, new sidewalk where there is none and updating ADA (American’s with Disabilities Act) pedestrian ramps. The existing asphalt pavement will either be: 

  1.  Reconstructed full depth, or 
  2.  Mill pavement between two and three inches then resurfaced with two or three inches of asphalt. Full depth pavement repairs will be performed as necessary

During the hot summer months temporary restoration in the right of way will be seed.  The contractor will be back in the fall for permanent restoration of sod.  Below is the list of streets, and their proposed improvements.  Please note that this list (and the proposed treatments) is only tentative and that streets may be deleted or added based on budgetary restrictions. 

Click here to view a full size map of the 2019 Residential Street Program and hover over your street for updates on the construction activities!

construction projects

Cedar Street (83rd Terrace to 85th Street)  curb repairs with mill/overlay

"On street" public meeting date March 25 at 5:30 pm for residents.

June 21: Restoration will be completed next week with sod placement at the new underdrain installation. 

June 14: Backfill and final restoration week of June 17th, weather permitting

June 4: Subgrade modifications being made this week with final in the near future. 

May 21: Subgrade on the north end of this project continues to degrade and requires more extensive modification.  Crews will return as weather permits for this activity.

April 30: Unacceptable subgrade material discovered on this street.  Friday activities included removal of this material and placement of base asphalt.  Crews will be back to place surface lift this week as weather permits.

 

 Cedar Drive cul-de-sac (off of Somerset) Project Complete

 

 Granada (81st to 83rd)

 "On street" public meeting date April 23 at 5:30 pm for residents mid block.

 June 21: Additional repair required on north end of project.  Scheduled for Tuesday with paving operation following.  Sod installation next week as well.

June 14: Unacceptable subgrade on the north 500 feet of the project is being repaired.  Base asphalt scheduled for early next week. 

June 4: East driveway construction continues tomorrow, weather permitting.

May 24: West side drives are open.  East side work will not start until weather permits.

May 21: Weather will play an important factor in completion.   Crews are currently working on West side driveways.

May 3: Sawcutting curb will begin.

 Windsor Drive (79th to Somerset)

 "On street" public meeting date April 24 at 5:30 pm for residents mid block.

June 21: Sod operations are scheduled after completion of Roe Avenue. 

June 4: Milling and Paving operations later this week, weather permitting. 

May 21: Weather will play an important factor in completion.  Crews are working on the last concrete item, sidewalk installation, before milling operations begin.

May 3: West side curb scheduled for Saturday.  Removals on East side will be next phase. Look for orange flyers in your yard to notify you of these impacts.

Apr 29: Sawcutting curb will begin on west side.  Look for orange flyers in your yard!

 Dearborn CDS

"On street" public meeting date May 15 at 5:30 pm for residents mid block.

 June 21: Milling and paving operations are scheduled for next week.

June 14: Concrete work starts late this week and is scheduled for completion next week with a mill and overlay following soon after. 

June 4: removals later this week, weather permitting. 

May 24: Weather has delayed start date.

 Norwood Drive (79th Street to Somerset Drive)

"On street" public meeting date May 14 at 5:30 pm for residents mid block.

June 21: Unacceptable subgrade found throughout the street.  Repairs start next week Tuesday. 

June 14: Backfill and restoration items remain.  These are scheduled for early next week with sod installed after Roe completion 

June 4: removals later this week, weather permitting.

May 24: Weather has delayed start date.

 Beverly (Tomahawk to 81st)

 "On street" public meeting date June 10 at 5:30 pm for residents mid block.

June 21: east side curb is in and most of the driveways are completed.  Driveway work was scheduled for completion today; however rains have stopped that activity.  Any driveway not completed has been given temporary access for the weekend. 

June 14: removals begin on the east side Monday, June 17th, weather permitting.

 84th Terrace (Juniper to Nall)

 "On street public meeting date June 11 at 5:30 pm for residents mid block.

 June 21: removals are scheduled for next week.  Please watch your yard for orange flyers.

 

 


UBAS Program

Concerns/questions?  Email the project team at ubaspv@pvkansas.com

General Information

2019 Program Contractor:McAnany Construction
Start Date:June 1, 2019
Construction Cost: $400,000 Completion Date: Fall 2019

Ultra-thin bonded asphalt surface (UBAS) is an asphalt surface treatment used to help extend the life of a road by placing a thin overlay onto a prepared asphalt surface.  The overlay can disperse water quickly off the surface, which reduces roadway spray from vehicles and provides greater visibility in wet weather. 

The contractor will patch the roadway as needed, mill the entire surface to remove roughness and apply the UBAS with a paving machine similar to asphalt overlay.  Access may be impacted to your driveway momentarily as the paving machine goes by the area.

Birch Street | 69th Terrace to  70th Terrace - Complete

Somerset | Roe to Nall - Complete

71st Street | Roe to Nall

Concrete Repair Program

Concerns/questions?  Email the project inspector at dthompson@pvkansas.com

General Information
Replacement of existing damaged or deteriorated concrete curb, sidewalk and ADA (American’s with Disabilities Act) pedestrian sidewalk ramps.

 2019 Program  Contractor: Kansas Heavy Construction
   Start Date:June 27, 2019
 Construction Cost: $700,000  Completion Date: Fall 2019

 Click here to download a larger map of the 2019 Concrete Repair Program.

2019 concrete map for website


 

2019 Street Repair Program

General Information
The City has created a program whereby a Contractor is hired to perform street repairs at various locations throughout the City. This program allows us to address areas where significant settlement or deterioration has occurred and make repairs to the roadway in those areas.  Click here to download a full size Pavement Repair map.

 2019 Program
 Contractor: Advanced Asphalt
   Start Date:Summer 2019
 Construction Cost: $150,000  Completion Date:August 31,2019

2019 Pavement Repair Map


 

MicroSurfacing/Crack Seal Program

Concerns/questions?  Email the project team at microcrack@pvkansas.com  This email goes to 4 members of the team at the City and Contractor.

General Information
Micro Surfacing is a mixture of emulsified (liquid-like) asphalt, aggregate, admixtures, cement and water that is applied in a thin coat as a maintenance tool to assist in preserving the existing asphalt pavement. It helps seal the existing surface and has a life span of approximately seven to ten years.  It is not considered a substitute for reconstructing or resurfacing the street, but rather a less costly solution in prolonging the existing pavement until major work is necessary and as funding becomes available.

The Contractor will be working on several streets throughout Prairie Village on the same day so we cannot tell you exactly what time the crew will begin on your street.  The first street they work on will be at 8:00 a.m.  After completing that street, they will move to others and will stop Micro Surfacing very early in the afternoon to allow the streets time to dry before the end of the workday.  Please keep in mind that weather is a factor in the schedule and drying time.  The material is very sensitive to water so the weather is monitored closely for pop-up storms. 

There are two very important issues at hand with micro surface:

  1. It is sensitive to water. Please turn off your sprinkler systems the day of the scheduled Micro Surfacing.
  2. Driving on the surface is not permitted until the micro surface is cured; for this reason the street must be closed for the day. Any one driving around the barricades or driving on the street prior to it being opened may be subject to damages.

Be on the lookout for changeable message boards and orange flyers 48 hours prior to work starting to let you know when the micro surface is scheduled for your street. 

 

Crack Seal is a hot applied flexible rubberized sealant used to seal cracks in the pavement to prevent water from entering the base and sub-grade.  Sealing cracks and joints extends the service life of the pavement.  Streets will not have to be closed for crack sealing; therefore no notification will be given.  Crack Seal is completed in the fall when the cracks have had time to expand to allow the material to enter the cracks entirely.  We anticipate the Crack Seal Program to begin in late October.

Please note that streets on the map may change based on available funding. 

2019 Micro-Crack Program  Contractor: Vance Brothers
   Start Date: May 2019
 Construction Cost: $312,000  Completion Date: November 2019
 View a full page map of the Micro Surface  streets or the Crack Seal streets.

 

 2019 Crack Map2019 Micro Map