Delmar/Fontana Low Water Crossing Removal and Flood Control Project

Print
Press Enter to show all options, press Tab go to next option

Project Overview

There is a long history to this project dating back to the 1998 floods. The attached City Council memo explains the history and this memo set the current direction of the project. Council voted to move forward with Option 1.

Below is a Council Memo requesting to submit a Preliminary Engineering Study to Johnson County for project funding.

Below is the most recent Council Memo for Final Design for the project

Updates

August 9 – Preliminary design continues for this project. Coordination has also begun with utility companies to plan utility relocation that may be required as part of the improvements. 

Individual resident meetings will begin in September to review the preliminary design with property owners adjacent to the improvements. After individual property meetings occur, a public meeting will be held to review the project and schedule.

Construction is currently planned to occur in 2019.

March 29 - Progress is being made and most of the field surveying is complete. Utilities have been located and surveyed. During the week of April 1, 2018, four locations will have soil borings taken to determine sub surface information. View the Soil Boring Location Map here (PDF). Once that is complete all the utility flags can be removed from properties.

We are now starting the detailed design based on Option 3 of the Preliminary Engineering Study. As we develop the design we may have meetings with individual properties along the way. Once preliminary design is complete we will have a resident meeting.

February 27 -
A letter was sent to residents of the neighborhood to make them aware of the current status of the project. View the letter here.